The worry I hear most about kitchen extension design is not whether it will look good. It is whether it will work. Will there be enough worktop? Will the dining end be dark? Will we spend all that money and still be tripping over each other at breakfast?

Those are the right worries, and they are answered by doing things in the right order. Here is the order I design a kitchen extension in, step by step, and why each step comes where it does. The earlier questions, such as whether you need planning permission and what it might cost, are covered in planning a kitchen extension.

Step 1: a brief built from how you live

A brief is not a list of features. It is a description of the day. Who cooks, and how often. Whether you eat at the table every night or perch at the counter. Where the children do homework. How many people come for Sunday lunch. Whether you need to see the garden from the sink.

A good brief also says what is wrong with the current kitchen, in plain words. “The fridge door blocks the route to the garden” is more useful than “we want an island”.

Step 2: an accurate drawing of what is there

A measured survey records the existing house exactly, including floor levels, ceiling heights, window positions and the drains. You commission it yourself, for about £1,000 to £1,500, paid directly to the surveyor, and some surveyors charge VAT on top. It usually takes a week or two. Designing from estimated dimensions is how a kitchen ends up 150 millimetres too long for the wall it was drawn on.

Step 3: two or three different options

Different in substance, not variations on one idea. One might extend across the full width. One might extend less and move the kitchen into the old dining room. One might not extend at all. Each gets a rough cost band and a plain note on the planning route.

This is the step people skip most, and it is where the biggest savings are found. It is also what the Clarity Pack does, with the options drawn as 2D layouts so you can compare them before anyone falls for one.

Step 4: the kitchen extension layout, tested in 3D

Once an option is chosen, the layout is worked out in detail: where the sink, hob and fridge go, the space between the island and the units, and the route from the hall to the garden. A gap of about a metre between an island and the run of units is a sensible starting point, a little more if two people cook at once or the dishwasher opens into it.

I build the scheme as a 3D model you can walk through in a web browser. It shows problems a plan hides, such as the island that blocks the back door, or the view from the sofa straight into the extractor. There is more on why that matters in how 3D design helps you decide before you build.

Step 5: light and structure together

Where the rooflights go depends on where the steel goes, and both depend on the layout. A rooflight close to the old back wall brings daylight into the middle of the house, which is the part a deep extension tends to leave dark. A wide opening into the existing rooms needs a beam, and sometimes posts, which have to land somewhere sensible. This is where the structural engineer comes in.

Think about orientation here too. A south or west-facing wall of glass can make the room too hot on a summer afternoon unless the roof oversails it or there is some shading.

Step 6: the planning route

Permitted development, a lawful development certificate or a householder planning application, depending on the house and the scheme. If an application is needed, councils usually decide within 8 to 12 weeks of validation, and the design is shaped around what the council is likely to accept rather than defended after a refusal.

A sitting room with a central fireplace, built-in timber shelves and floor-to-ceiling glazing onto the garden.

When should the kitchen designer get involved?

Somewhere between steps four and seven, and earlier than most people think. Most kitchens are designed by the supplier, and most suppliers only see the drawings once the building is designed. By then some decisions are hard to undo.

The things that need agreeing early are surprisingly practical:

  • where the extractor ducts to, because an island hob under a flat roof needs a route out, and that route crosses joists
  • where the island gets its power and, if it has a sink, its drainage, because a waste pipe needs a fall and the floor build-up has to allow for it
  • window and door positions against the run of units, so a tall larder doesn’t end up in front of a window
  • underfloor heating and the floor finish, because they set the finished floor level and the threshold to the garden

None of that is difficult if it is dealt with early. All of it is expensive to change once the slab is down. The same goes for the utility, the boot room and the built-in storage around the kitchen, which is where interior architecture and the building design meet.

Step 7: drawings a builder can price

Planning drawings show what the building looks like. A builder needs to know how it is built: the foundations, the steel, the roof build-up, the drainage, the window schedule and the finishes room by room. The Technical Pack provides that, coordinated with the engineer and with building regulations, so every builder prices the same thing. How the stages fit together is set out on the kitchen extensions page.

Step 8: the tender and choosing a builder

The package goes to a small number of builders, their questions are answered and shared with all of them, and the returns are compared line by line. The cheapest number is not always the best value, and a written comparison makes the differences visible. Choosing the right builder goes further into this step.

How long does it take to design a kitchen extension?

The survey takes a week or two. Developing the design in 3D usually takes three to five weeks of back and forth. A planning decision, if you need one, takes 8 to 12 weeks, and the technical drawings and tender come after that. For a whole project, from the first call to moving back in, 12 to 18 months is realistic. That surprises people, but most of it is design, planning and tendering, and that time is what makes the build itself go smoothly.

On cost, the Surrey benchmark for extension building work is £2,500–£3,500 per m² of new floor area, before VAT, with specification, site conditions and a contingency of 10–15% moving the number. It is a range, not a quote. The kitchen itself is on top, and the extension cost calculator adds the two together for your own size and specification.

If you’d like to talk through your own kitchen before step one, book a free 15-minute Clarity Call.

Questions people ask about designing a kitchen extension

How much space should there be between a kitchen island and the units? About a metre is a sensible starting point, and a little more if two people cook at once or the dishwasher door opens into the gap. Less than that and the island starts to block the route through the room, which is the first thing a walk-through in 3D tends to show up. Test it with the real appliance sizes rather than guessing, because the difference between a comfortable island and an awkward one is small.

Where is the best place for a rooflight in a kitchen extension? Close to the old back wall, where the extension meets the existing house. That is the part of a deep extension that tends to end up dark, and a rooflight there pushes daylight into the middle of the plan. Glass at the far end of the room does far less for it. Think about orientation too: a south or west-facing wall of glass can overheat the room on a summer afternoon unless the roof oversails it or there is some shading.

Do I need a structural engineer for a kitchen extension? Almost always, because the point of a kitchen extension is usually a wide opening between the new room and the old ones, and that needs a beam and sometimes posts that have to land somewhere sensible. Where the steel goes also decides where the rooflights can go, so the engineer’s input belongs at design stage, not after. Their calculations then feed the technical drawings that building control checks and builders price from.

Journal by email

New articles, sent to you

New posts, a few times a month. No fees, no selling. Unsubscribe in one click.

We use your details only to send you the journal, as described in our privacy policy, and never share them.

The service this relates to

The cover photograph of Your Dream Home: a bright kitchen extension in Walthamstow

Free guide

Your Dream Home

Doing this for the first time? Thirty-eight pages on getting the order right: the five mistakes to avoid, what it really costs in Surrey, how planning works and how long it takes, with two worksheets to fill in.

Get the free guide

If you are weighing this up for your own home

Fifteen minutes on the phone with James. There is no pressure and no obligation. Sometimes the right outcome of a call is simply a clearer head.

Book a free 15-minute Clarity Call (opens in a new tab)

James calls you at the time you pick. You describe the house and what you want to do; he tells you what he would do first and whether a Clarity Pack is worth it. No preparation needed.

No selling. Just a clear view on the smartest next step. Prefer to write? Send a short note.

Accreditations

  • RIBA Chartered Practice
  • ARB registered architect, registration number 088216J
  • AECB member
  • Passivhaus Trust member
  • LABC Registered Partner, Partner Authority Scheme
  • Woking Chamber of Commerce member

Enlarged picture