Most people come to a renovation with a list. A bigger kitchen, another bathroom, somewhere to work that isn’t the dining table. What they don’t have is an order to do things in, and that is where the money tends to go wrong.
The usual route is to ask a builder round, get a price for the thing on the list, and start. Sometimes that works. Often it means the most expensive decision, what to build, gets made before anyone has checked whether it is the right one.
So this is how to plan a home renovation, step by step: the sequence I would follow for almost any renovation or extension in England, from first idea to moving back in.
How long does a home renovation take?
On a typical project it takes 12 to 18 months from the first call to being back in the house, and a good part of that time is spent before anyone picks up a shovel. Design, a planning decision of usually 8 to 12 weeks, technical drawings, building control and the builder’s start date all come before the build itself. None of it is fixed, and some of it is in other people’s hands.
Before anything is drawn
1. Work out what is actually wrong
Start with how you live, not what you want to build. Walk through a normal weekday. Where does everyone end up at 7.30 in the morning? Which room do you never use? Where does the daylight run out? Where do the shoes, bags and post pile up?
Write it down. The list usually turns out to be about flow and light more than floor area.
Jeremy and Mary-Jane in Guildford are a good example. Every builder they spoke to said the same thing: knock through and extend into the garden. When we walked the house, the real problem was the way the rooms connected, not the amount of space. The scheme they built was smaller than the one the builders had proposed.
“It’s changed how we live. We still regularly have to pinch ourselves.” Jeremy, Guildford.
2. Be honest about the budget
Decide what you can spend in total, including VAT, fees and a contingency, before you see any designs. Designs grow to fill whatever budget nobody has written down.
As a guide, a Surrey extension runs at roughly £2,500 to £3,500 per m² of new floor area, before VAT. Specification, site conditions and a contingency of 10 to 15% all move that figure. Most building work to an existing home carries VAT at 20%, so always check whether a number includes it. On whole projects we have tendered in 2025 and 2026, a small single-storey extension with a rewire, new heating and redecoration came back at £125,000 to £135,000, excluding VAT and rounded. That gives you a feel for how quickly the numbers add up once the rest of the house is involved. The extension cost calculator lets you try your own figures.
3. Test the options before anyone draws them properly
This is the step most people skip. Before committing to detailed drawings, look at two or three different ways of solving the problem: extending, reorganising what is already there, or a mix of the two. Check each one against the structure, the planning position and a cost band.
That is what our Clarity Pack is for. It is a short piece of work, from £1,500 + VAT, that tests what is realistically achievable on your house and ends with a written recommendation and a roadmap. It isn’t a planning application or a commitment to the whole project. Its job is to stop you paying for drawings of the wrong scheme.
From drawings to moving back in
4. Design and planning
Once the direction is clear, the scheme is developed and, where needed, submitted for planning.
Some work doesn’t need a planning application at all. Permitted development rights let you extend a house within set limits, and most internal changes need no permission. If you go that way, a lawful development certificate from the council is worth having as proof. Other work needs householder planning permission, particularly in conservation areas, on listed buildings, or where the house has already been extended. Listed buildings also need listed building consent for most changes, inside and out. Permitted development vs planning permission explains where the line usually falls.
A householder application usually gets a decision 8 to 12 weeks after the council validates it. Nobody can promise the outcome. What you can do is design with the council’s policies in mind from the first sketch, so the scheme is defended, not rescued.
98% of the sites we have taken through planning since 2020 gained permission in the end: 79 of 81. Planning figures cover 108 decisions on 81 sites, March 2020 to October 2026, from council notices and our own records. Three appeals were allowed.

5. Technical drawings and building regulations
Planning permission says what the building can look like. It says very little about how to build it. A builder pricing from planning drawings is filling the gaps with guesses, and guesses come back later as extras.
Technical drawings set out the structure, the construction at each junction, insulation, drainage and the specification, room by room. They go to building control, either the council or a registered building control approver, who check them against the building regulations and inspect the work on site. Building regulations apply whether or not you need planning permission. Planning permission vs building regulations sets out the difference.
Most projects need a structural engineer. If you share a wall with a neighbour, or dig near their foundations, the Party Wall etc. Act 1996 probably applies, and notices go out before work starts. On projects with more than one contractor, the CDM Regulations 2015 require a principal designer to plan and manage health and safety during the design.
This is also the stage to settle insulation, ventilation and heating, while they are still lines on a drawing. A renovation is the cheapest moment to make an older house warmer.
6. Choose a builder from a proper tender
With a full set of technical drawings and a specification, you can send the same package to three or four builders and compare like with like. Without it, every quote is pricing a different building, and a low price on a thin package usually just means more of the job hasn’t been priced yet.
Ask how they handle variations, who runs the site day to day, and what the payment stages are tied to. Use a written contract. Choosing the right builder has the full list of questions.
7. The build
Allow for surprises, because old houses hide things. That is what the contingency is for. Make decisions on fittings and finishes before the builder needs them, not on the day. Late decisions cause more delay than bad weather, which is one of the five ways to avoid renovation regret.
Keep an eye on variations. Nothing extra should be started without a price agreed in writing first.
8. Finishing properly
At the end there is a snagging list, the building control completion certificate, electrical and gas certificates, and guarantees for things like windows and the boiler. Keep them together. You will need them when you sell.
What is the order of works on a house renovation?
Once the builder starts, the work on site follows a sequence of its own, and knowing it helps you see whether a programme is realistic and when each decision is needed. On a typical renovation with an extension, the order is:
- Set up: scaffold, skips, protection to the parts of the house you are keeping, and the party wall notices already served.
- Strip-out and demolition, including the removal of anything that is being replaced.
- Groundworks and foundations for any new structure, and drainage below the new floor.
- Structure: steels, new openings, the new walls and the roof, until the building is weathertight.
- Windows and external doors, so the inside can dry out and the trades can work in any weather.
- First fix: electrics, plumbing, heating pipework and ventilation ducts, run before anything is covered.
- Insulation, plasterboard and plastering, then the screed or new floor structure.
- Second fix: sockets and switches, sanitaryware, the kitchen, internal doors and joinery.
- Decoration, then the floor finishes that scratch easily, then the snagging list.
- Certificates: building control completion, electrical and gas, and the guarantees, kept together for when you sell.
Kitchens, bathrooms and fittings need choosing before step 6, because the first fix is set out around them. That is the single most common cause of delay on a renovation, and it is entirely avoidable.
The process page sets out how these stages fit together when we work on them with you. If you are at the list-writing stage now, the free 15-minute Clarity Call is a good place to talk it through.
Questions people ask about planning a renovation
What should you do first when renovating a house? Work out what is actually wrong with how the house works, set a total budget that includes VAT, fees and a contingency, and test two or three ways of fixing the problem against that budget before anyone draws the scheme in detail. The builder comes after those three, not before.
Do you need an architect for a renovation? Not for redecoration or a like-for-like kitchen. For anything that moves walls, changes the outside, needs planning permission or needs building control, you need someone who designs buildings, and an architect also runs the order of decisions so that the design, the planning route and the budget agree before the build.
In what order should renovation work be done? Strip-out, then structure and anything that makes the building weathertight, then the first fix of services, then plaster and floors, then second fix, decoration and finishes. Design decisions on fittings have to be made before the first fix, which is why the planning stage matters more than the building stage.