Projects · Dartmoor, Devon
Dartmoor reception building
A replacement reception, shop and office for a holiday park on the western edge of Dartmoor, clad in timber under a natural slate roof.
The problem
The building had no foundations, the floor joists sat on loose brick over soil, and it could not be insulated properly by re-cladding.
The decisions
- Replace, do not re-clad.
- Keep to one simple roof.
- Put the office in the roof.
- Move it when the regulations asked for more.
The result
We have taken the building through planning with the National Park Authority twice: in September 2022 for the first design, and in June 2024 for the larger one in its new position.
This is a working building: the reception, shop and office of a holiday park on the western edge of Dartmoor National Park.
The old building had grown since the 1950s. It was an uninsulated timber shed with a metal container attached, under one slate roof. It was the park’s office all year, and its shop and guest reception from March to October. The first plan, in 2021, was to keep it, re-clad it and put solar panels on the roof. Surveys in 2021 and 2022 changed that. The building had no foundations, the floor joists sat on loose brick over soil, and it could not be insulated properly by re-cladding. It had to be replaced.
We designed the replacement on a similar footprint. The ground floor holds the shop and reception, a meeting room, a kitchen and a WC. Stairs lead to an office in the roof.
The building is one simple pitched-roof form, clad in timber with a natural slate roof, close to the pitch of the building it replaces. The entrance is recessed into the east gable for shelter. The ridge is about 2 metres higher than before, to fit the office upstairs. The parish council noted the height and supported the scheme.
The National Park Authority approved it in September 2022. Its conditions deal with materials and lighting: natural slate nailed to the roof, timber left to weather or stained dark, black-framed solar panels, and no new outside lighting without approval.
The building regulations stage then changed the design. A wheelchair-accessible WC and a compliant stair needed more room, and new rules on electric vehicle charging needed space in the car park. The building grew 1.7 metres wider, 0.4 metres deeper and 0.2 metres higher. It moved about 8 metres south onto lower ground, which offsets the extra height.
We have taken the building through planning with the National Park Authority twice: in September 2022 for the first design, and in June 2024 for the larger one in its new position.
The decisions
Replace, do not re-clad. Surveys showed the old building had no foundations and could not be insulated properly by re-cladding, so we designed a replacement on a similar footprint.
Keep to one simple roof. One pitched-roof form, clad in timber with a natural slate roof, close to the pitch of the building it replaces.
Put the office in the roof. The ridge is about 2 metres higher than before, to fit the office upstairs.
Move it when the regulations asked for more. We redrew the building for the wheelchair-accessible WC, the stair and the car charging, and moved it about 8 metres south onto lower ground, which offsets the extra height.
The pictures on this page are our visualisations of the 2024 design, the one that was approved that June. They are not photographs of a finished building.