Projects · Bosham, West Sussex
Bosham extension and timber cladding
A rendered house reclad in black timber, with a single-storey extension in natural timber under a deep flat roof. Designed by Martin Swatton Design, with our technical design, Building Regulations and construction drawings.
The problem
The ground brought two complications: a high water table, known before work started, and an existing soakaway found on site that nobody expected.
The decisions
- Turn the design into a building.
- Coordinate three jobs on one house.
- Design around the ground.
- Write it down room by room.
The result
The extension is the reverse of the house in colour, with the same boards left natural under a flat roof that reaches out over the terrace.
Martin Swatton Design conceived and designed the complete scheme through to planning for his clients, collaborating with James Williamson Architects, who provided the technical design, the Building Regulations submission and the tender and construction drawings.
The house was built in the late 1990s and added to in the mid 2000s. The project had three parts: a single-storey extension at the back, new timber cladding to the outside of the house, and a new layout and finishes inside.
Martin’s design changed the look of the whole house. The white render was covered with vertical timber boards painted black, and the clay roof tiles were kept. The extension is the reverse of the house in colour, with the same boards left natural under a flat roof that reaches out over the terrace. The underside of that roof is lined in timber. Sliding glazed doors open the kitchen, dining and living room to the garden. At the front, the old porch was replaced with a simple canopy.
Our work was to turn that design into a building, and it was a complicated project to coordinate: an extension, new cladding to the whole house and a new interior, three pieces of work on one house, drawn so that the designer, the structural engineer and the builder were all working from the same information. We drew the demolition plans, the setting-out plans, the sections through the extension and the details at the junctions: where the roof meets the glazing, where the cladding meets the windows, and how the floor runs out to the terrace. We wrote the specification and the schedule of works room by room, prepared the window and door schedules, coordinated the drawings with the structural engineer and submitted the work to Building Control under a building notice.
The tender set of 41 drawings was issued in January 2024, and the build was on site later that year. The ground brought two complications: a high water table, known before work started, and an existing soakaway found on site that nobody expected. We designed the slab edge and the thresholds for the water table with the structural engineer. The routing of the soakaway had to be established, and we revised the drainage drawings while the work carried on. The photographs were taken in 2025.
The decisions
Turn the design into a building. A tender set of 41 drawings: demolition and setting-out plans, sections through the extension, and a detail for every junction, from the roof and the glazing to the cladding and the terrace.
Coordinate three jobs on one house. The extension, the cladding and the new interior were drawn together, with the structural engineer’s work in the same set, so nobody on site was working from a different answer.
Design around the ground. We knew about the high water table before work started, and designed the slab edge and the thresholds for it with the structural engineer. The surprise on site was an existing soakaway: its routing had to be established, and we revised the drainage while the build carried on.
Write it down room by room. The specification and the schedule of works, with the window and door schedules, gave the builder one account of the job to price and to build.
Keep drawing to the end. We issued further details as the building went up, each one answering a question from site.